Please be informed that the National Grid Corporation of the Philippines (NGCP) is scheduling a power service interruption on October 23, 2024 (Wednesday).

 

Date: October 23, 2024
Time: 6:30AM-7:00AM & 5:30PM-6:00PM
Affected areas: Whole town of Botolan

Reason:
Momentary outage for shifting and isolation of loads.

Replacement of insulators at the isolated segment.

 

• Taugtog S/S connected to Botolan S/S

• San Felipe S/S connected to Olongapo S/S

 

Momentary outage for shifting and isolation of loads (Normalization).
• San Antonio S/S connected to Botolan S/S

• San Marcelino S/S connected to Olongapo S/S

 

In case you or your customers will operate standby generator set/solar during shutdown, please make sure to trip-off/open your respective breaker/isolator going to our line to ensure safety of our maintenance personnel.

 

Please consider our lines always energized as we shall restore electric service without prior notice. Thank you.